The
Warden of the California State Prison at Los Angeles turned
to Vector Strategies when faced with the challenge of building
a large medical facility inside the prison. This 200-bed
mental health hospital was much larger than any project previously
attempted.
The TOC Critical Chain project management solution and
use of the logical tools allowed them to open the hospital
within six months. Two other facilities using
non-TOC approaches failed to match their results even after twelve months of
effort.
|